DOL updates PERM processing times
published 09 September 2010

The U.S. Department of Labor recently posted updated PERM processing dates.  DOL reports that as of August 31, 2010, it was processing the following PERM cases:

   Analyst Review:  May 2010 
   Audit Review:  August 2008 
   Standard Appeals:  March 2008
   Government Error Appeals:  Current

The Analyst Review queue moved forward six months, and both Audit Review and Standard Appeals moved forward one month from the dates reported at the end of July 2010.

Cases in “Analyst Review” are undergoing initial review – these are the cases for which DOL is currently issuing certifications and audit notices. While DOL reports that it is processing cases filed in May 2010, we are aware that cases filed as late as August 2010 have recently been processed at DOL. DOL's only explanation for this variation in processing times is that "For various reasons, we may be completing the processing of applications filed prior to the month posted on iCERT."

Cases in “Audit Review” were issued audit notices by DOL, and the employer submitted an audit response to DOL for review. It is impoFor example, DOL is reviewing audit responses for PERM cases that were filed in August 2008 and earlier; however, the employer’s audit response may have been submitted several months after that date.

Cases in “Standard Appeals” are denied cases where either a request for reconsideration by DOL or a request for appellate review (i.e., an appeal) was submitted. DOL now forwards appeals directly to the Board of Alien Labor Certification Appeals (BALCA) for review; however, until late 2009, DOL was processing both reconsideration requests and appeals in the same queue, so the "Standard Appeals" queue includes both requests for reconsideration and appeals.

Government Error Appeals” are appeals based solely on an error by DOL, i.e., cases denied for failure to respond to an audit, but the employer did in fact submit a timely audit response. While an employer may ask for its appeal to be considered under the government error queue, DOL is the sole arbiter in determining whether the decision was government error. If DOL does not find that the decision was erroneous, the case will move to the Standard Appeal queue for further processing.

The progress in the processing times reflects DOL’s efforts to reduce its pending backlog of PERM cases. DOL’s production goal for FY 2010 is to reduce the backlog by 50% by the end of September 2010. DOL states that if a pending application was filed more than three months prior to the reported processing month, an inquiry may be made on the status of the pending application. Whether a case is behind the processing times will depend on what processing queue the case is in at DOL. For example, under the DOL’s standards, a case filed in August 2009 would be overdue for initial Analyst Review (May 2010), but not overdue under the Audit Review (August 2008) processing date.

Jackson & Hertogs is monitoring the status of our pending PERM cases, and following up with DOL when cases are behind the reported processing times.